table of contents

Summer 2006

 


Ocean Center expansion delayed by construction bids way beyond budget


Site work for the Ocean Center expansion is well under way

The start of vertical construction of the Ocean Center expansion project will be delayed by at least four months because original bids received by the project’s builder are several million dollars over budget.

“We’re doing everything possible to keep this project on track,” said County Chair Frank Bruno. “But we’re dealing with a construction market where costs are escalating so rapidly that it’s hard to budget for anything you’re planning to build.”

County officials faced the news in March that bid responses from subcontractors submitting proposals for the expansion project’s components were several million dollars over budget and there were no bid responses for major elements of the project’s construction.

Site work for the expansion of the Ocean Center is well under way and vertical construction was scheduled to start early this summer. The county has $63 million budgeted for the project. “The contractor has rejected all bids,” said Assistant County Manager Matt Greeson. “There’s no doubt we are delaying the start of vertical construction.”

The prime contractor, Hardin Construction Co., Atlanta/Peck and Associates, Daytona Beach, has re-bid the construction packages in an effort to encourage a greater number of bidders from a wider area. Hardin is using the bids as the basis for a guaranteed maximum price which is to be submitted to the county.

Phase I work -- a new south parking lot adjacent to Peabody Auditorium -- was completed last year. Phase II – site and civil engineering work – began almost immediately after that. Construction fences went up and grading began, followed by preparation of deep foundations and the setting of pilings.

Completion of the expansion is slated for 2008 and will yield a complex roughly twice the size of the present facility. Square footage will increased to more than 500,000 including 164,000 square feet of exhibit space, up from the present 60,000 square feet total. In fact, when the expansion is complete, the Ocean Center will rank as the fifth largest complex in Florida, up from its current rank of 17th.

The Ocean Center expansion is seen as a key element of the county’s future tourism and the rejuvenation of the core beachside of Daytona Beach. The project’s $63 million price tag is being financed with resort taxes.


Department of Economic Development
700 Catalina Drive, Suite 200, Daytona Beach, FL 32114
Telephone:
386-248-8048   FAX: 386 238-4761   Toll Free: 800-554-3801

Phil Ehlinger
Director

doed@volusia.org